Afternoon install

Stage 3 – Home stretch and back into production line
  • 2 men sorting pre-cut and numbered floor joists ready for installing as per Spantec working drawings.
  • 2 men placing floor joists into joists hangers (framing brackets).
  • 2 men screw fixing joists in main floor area followed by set down wet areas.
Stage 4 – 5 pm finish (incl. 15 min lunch)
  • Check floor frame is square in case of any movement during installation
  • Final check and adjustment to pier heights to make sure floor is level
  • Bolt remaining Ezipier bases to concrete pads and screw fix remaining Ezibrace cross bracing
Victorian House Episodes:

Episode 1 – Sunday 30 April 2017
Episode 2 – Monday 1 May 2017 
Episode 3 – Tuesday 2 May 2017 
Episode 4 – Tuesday 2 May 2017

GENERAL ENQUIRY

-or- Get a quote

  • This field is for validation purposes and should be left unchanged.

Click to share

Share page?

×
Enquire Now